‘Complete Dindi in 6 months, Palamuru-RR by year-end’
[ad_1]
₹2,000 cr. to be launched for clearing pending payments of initiatives
Chief Minister K. Chandrasekhar Rao has instructed engineers of the water assets division to hurry up works on Palamuru-Rangareddy and Dindi raise irrigation schemes geared toward offering irrigation facility and assembly consuming wants in the rain-shadow and fluoride-hit areas of mixed Mahabubnagar and Nalgonda districts.
In a evaluation assembly held right here on Saturday, he needed the engineers to finish main works of Dindi in the subsequent six months and of Palamuru-Rangareddy works by the year-end. He informed the officers that the 2 initiatives shall not face any shortage of funds and the federal government would allocate enough funds for them in the approaching finances too.
“The State Government has taken a historic decision to ensure speedy execution of works by empowering the officials/engineers at different levels to sanction emergency works with limited expenditure without the necessary of waiting for decisions at state-level”, the Chief Minister famous.
Stating that nowhere in the nation such a switch of energy was given, the Chief Minister stated Engineer-in-Chief may approve works as much as ₹25 crore a yr with every work not exceeding the price of ₹1 crore. Similarly, Chief Engineers may approve works as much as ₹5 crore a yr with with the price of each work taken up not exceeding ₹50 lakh.
Further, Superintendent Engineers may sanction works price ₹2 crore per yr with the price of every work not exceeding ₹25 lakh, Executive Engineers as much as ₹25 lakh with every work not exceeding ₹5 lakh and Deputy EEs as much as ₹5 lakh with every work not exceeding ₹2 lakh, the Chief Minister stated and steered correct utilisation of the ability to take up pressing works and full them in time.
The Chief Minister directed the officers to merge the ‘Maskuris’, village-level panchayat employees, with the Water Resources Department and utilise their companies as ‘Lashkars’ after giving vital coaching in venture/water assets administration.
During the component-wise evaluation of Palamauru-Rangareddy venture, the Chief Minister enquired concerning the standing of Narlapur reservoir and pump-house, Narlapur-Yedula canal, Yedula pump-house, Yedula-Vattem canal, Vattem reservoir, Vattem-Karivena canal, Karivena reservoir, Kairvena-Uddandapur canal together with tunnel.
The Chief Minister instructed Principal Secretary (Finance) K. Ramakrishna Rao to launch ₹2,000 crore instantly to clear Palamuru-Rangareddy and Dindi initiatives’ pending payments.
He directed the District Collector of Nagarkurnool, Nalgonda and Rangareddy to pay compensation to these whose lands have been being acquired for the 2 initiatives. He needed fee of compensation as per the legal guidelines and full the land acquisition on the earliest.
He additionally instructed Principal Secretary (Water Resources) Rajat Kumar to order the motors required for the 2 initiatives from BHEL and monitor their set up/erection.