Eshwarappa puts focus on Jala Jeevan Mission
[ad_1]
K.S. Eshwarappa, Minister for Rural Development and Panchayat Raj, has given one month’s time to officers to start 155 works with detailed challenge experiences (DPR) underneath the Jala Jeevan Mission.
He chairing the event progress evaluation assembly in Yadgir on Friday.
“Prime Minister Narendra Modi aims to provide tap water to every household under this dream project in the next four years. Officials have to take this task seriously to complete it in 100 days,” the Minister stated.
Officials of the Rural Drinking Water Supply and Sanitation Department stated the district has deliberate to implement 155 works which have DPR. Tender for 119 works had been floated. Agreement for 56 works accomplished and 51 works have commenced. He additional stated tender for 18 works might be floated in per week.
L.K. Ateeq, Principal Secretary of RDPR, stated faculties and anganwadi centres needs to be supplied water for consuming and bathroom, within the subsequent 100 days.
Officials stated that water was being provided to 190 anganwadis and faculties out of 417 in Yadgir, 155 anganawadis and faculties in 456 in Shahapur and 90 anganwadis and faculties accomplished out of 540. When he noticed the poor performances underneath Jala Jeevan Mission, Mr. Eshwarappa misplaced his mood and informed officers: “Are you not ashamed of not implementing the project properly?”. He set March 26 because the deadline to finish the challenge. The Minister additionally requested Shilpa Sharma, Chief Executive Officer, to oversee the challenge and name an officers’ assembly to evaluation the progress solely underneath Jala Jeevan Mission.
‘Ensure water supply’
Mr. Eshwarappa instructed officers to finish ongoing consuming water initiatives inside the date stipulated and guarantee consuming water to the agricultural areas successfully. He informed officers to drift tenders for 213 initiatives underneath Jala Jeevan Mission scheme.
The Minister advised to Ganapathi Sakre, government engineer of the division, when he defined that underneath the mission, it was aimed to supply consuming water by means of faucets to 83,480 homes within the district and 313 works for provide of consuming water had already been taken, DRP for 307 works was ready. 297 works had received administrative and tender for the works was floated.
“Your work will not be complete until you ensure potable drinking water to people,” he stated, and added that officers ought to submit recent proposals if any as there is no such thing as a dearth in funds for consuming water initiatives.