Replacement of sluice gates at KRS hit by COVID-19
[ad_1]
The alternative of 136 sluice gates at the Krishnaraja Sagar (KRS) reservoir throughout river Cauvery has been affected as a result of COVID-19 and restriction on the use of oxygen for industrial functions when the second wave of the pandemic peaked throughout April and May.
The alternative of all of the gates was to be accomplished by June 2022, however work slowed down because of the pandemic and is more likely to be accomplished by June 2023, stated Shankare Gowda, Chief Engineer, Irrigation (South), Mysuru.
The fabrication of the sluice gates is being taken up close to the dam. Though a letter was despatched to the workplace of the Deputy Commissioner in Mysuru to make sure provide of oxygen for this goal, it was not cleared because of the medical disaster, which peaked throughout April and May.
To enhance lifespan
KRS was one of the 22 dams accredited underneath Dam Rehabilitation and Improvement Project (DRIP) in Karnataka for taking on each structural and non-structural measures to increase its lifespan and improve dam security. The venture, funded by the World Bank, entails an expenditure of ₹58.46 crore to interchange 136 sluice gates and is being applied by Karnataka Water Resource Department (KaWRD). It is being executed by M/s Hardware Tools and Machinery Projects Pvt. Ltd., Gujarat.
Of the 136 sluice gates, 25 spanning totally different ranges alongside the reservoir have been changed up to now following third occasion inspection and approval that included World Bank consultants and the State Project Management Unit. Another eight gates, which have acquired approval following inspection, are prepared for set up.
Though 16 sluice gates at 80+ toes stage had been changed in 2011 by Karnataka, it was a minor train in comparison with the present venture. Work on this scale is being taken up for the primary time since completion of the dam in 1932.
Impact of rains
The bulk of the work at the dam takes place throughout the dry season. Now that influx to the reservoir has elevated because of the onset of the south west monsoon, the train will cease. But in case the monsoon is weak this yr and the water stage goes under the 100 toes mark by December, then the train can resume, in line with officers.